In Ohio, unpaid contractors, subs, laborers and suppliers can put a mechanics lien on the property they improve. On most jobs the owner records a notice of commencement before work starts, and subs and suppliers who don't contract directly with the owner send a notice of furnishing within 21 days of their first work. Liens on one- or two-family homes must be filed within 60 days of your last work, 75 days on most other jobs. Custom homes and remodels for an owner who lives there follow special rules.

What Is a Mechanics Lien in Ohio?

A mechanics lien is a claim against the property you worked on that secures payment for your labor or materials. Ohio's rules are in Ohio Revised Code chapter 1311.

Under section 1311.02, these people can have a lien:

  • Original contractors: anyone who contracts directly with the owner. That's you, the builder or remodeler.
  • Subcontractors: anyone who works on the job under a contract with someone other than the owner.
  • Laborers: the individual workers doing the work.
  • Material suppliers: anyone who furnishes materials for the job. Section 1311.12 says materials delivered to the site are presumed used on the job.

Home Jobs Play by Different Rules

First, figure out which kind of job you have. Section 1311.011 sets special rules for a "home construction contract": a contract between an original contractor and an owner to build or improve a single- or double-family home (or condo unit, or a garage, porch, pool or similar work next to it) that the owner uses or plans to use as their residence. Most custom home and remodeling contracts fit. On those jobs:

  • No notice of commencement is required (section 1311.04(O)), except that the owner may record one when the construction lender requires it.
  • No notice of furnishing is required (section 1311.05(E)), even when the lender has the owner record a notice of commencement.
  • Full payment protects the owner, and sub liens are capped at what the owner still owes you, minus the cost to finish the contract. More on that below.
Type of jobNotice of commencementNotice of furnishingLien deadline
Custom home or remodel for an owner who lives there (home construction contract)Only if the lender requires itNot required60 days after last work
Other one- or two-family home (for example a rental)Owner records it before work startsRequired from most subs and suppliers60 days after last work
Spec home on your own lotGenerally you, as owner, record it before work startsFrom subs and suppliers who don't contract directly with you60 days after last work
Commercial and most other private jobsOwner records it before work startsRequired from most subs and suppliers75 days after last work

On a spec home you build on your own lot, the statute's wording makes you the owner who contracts for the work, so the notice of commencement duties in section 1311.04 generally fall on you. Ask your attorney how the rules apply once you sell the house.

The Notice of Commencement

The notice of commencement tells everyone on the job who the owner, original contractors and lenders are, and where to send notices. Section 1311.04 sets the rules.

Who files it, where and when

The owner (or lessee) who contracts for the work records it with the county recorder in each county where the property is, before any labor, work or materials go into the job. One notice covers one improvement. If the owner adds original contractors, lenders or sureties later, they amend it.

The recorder charges the standard state recording fees. In Stark County, for example, mechanics liens and similar documents cost $34 for the first two pages and $8 for each page after that.

What goes in it

It's a sworn affidavit with the property's legal description, a short description of the work, the owner (and fee owner if different), the owner's designee if any, all original contractors, the date of the first contract with an original contractor, all lenders and payment bond sureties, the preparer, and two required statements: one to lien claimants and one on expiration. On a single- or double-family home with several original contractors, the owner can just say there are multiple.

Posting, copies and expiration

  • Post it on site. The owner keeps a copy posted in a conspicuous place on the property while the physical work goes on.
  • Copy to you. The owner serves a copy on the original contractor.
  • Copies on request. When a sub, supplier or laborer asks in writing, the owner, or the contractor or sub they contract with, sends a copy within 10 days.
  • Four-year life. Since September 30, 2025, a notice of commencement expires four years after it's recorded unless it says otherwise. The earlier version said six years.
  • Completion affidavit. The owner can now record an affidavit that the work is complete, which marks the notice expired. The owner must then mail a copy to the original contractor and anyone who sent a notice of furnishing.

When the owner doesn't file it

You can ask the owner in writing to record, serve or post the notice. If they don't within 10 days, they're liable for damages and costs from valid liens that proper payment could have avoided. If it still isn't recorded by the later of 10 days after work starts or 3 days after your written demand, you may record it for them, and the owner owes your costs. Without a recorded notice, subs and suppliers don't need a notice of furnishing to keep lien rights, so skipping it protects no one.

The Notice of Furnishing

The notice of furnishing tells the owner a sub or supplier is on the job and may have lien rights. The form in section 1311.05 warns the owner about "the possibility of paying twice."

  • Who sends it: subcontractors and material suppliers who don't contract directly with the owner, once a notice of commencement has been recorded.
  • Who doesn't: original contractors, laborers, and suppliers who contract directly with the owner. Nobody sends one on a home construction contract.
  • Who gets it: the owner's designee named in the notice of commencement (or the owner if none is named) and the original contractor. A sub or supplier who contracts directly with you doesn't have to serve you.
  • Deadline: within 21 days after first performing work or furnishing materials, or 21 days after a late-recorded notice of commencement is recorded or a requested copy is sent.
  • Sent late: it still counts, but it only protects work and materials from the 21 days before it was served and after. Earlier amounts lose lien rights.
  • How: section 1311.19 allows certified or registered mail, overnight delivery, hand delivery or another method with written proof of receipt. For certified mail, service is complete on the mailing date.

For a builder, notices of furnishing show which subs and suppliers say they're on the job, so you know whose releases to collect.

Deadlines to File a Lien and How Long It Lasts

To claim a lien, you file a sworn affidavit with the county recorder (section 1311.06) showing the amount due, the property, the owner, who you worked for, and your first and last dates of work.

StepDeadlineSection
File the lien affidavit: one- or two-family home or condo unit60 days from your last labor, work or materials1311.06(B)(1)
File the lien affidavit: most other jobs75 days from your last labor, work or materials1311.06(B)(3)
Serve a copy on the owner or designeeWithin 30 days after filing. If that fails, post it on the property within 10 more days1311.07
Lien stays in force6 years after filing, or until the court case ends if you sue within that time1311.13(C)
Sue after a notice to commence suit60 days after the notice is served, or the lien is void1311.11(B)

A lien can also be moved off the property onto a court-approved bond of double the claim, or one and a half times the claim if it's over $5,000.

Lien Releases, Affidavits and Bank Draws

Lenders don't want liens on the house that secures their loan, which is why lien waivers are on the list of documents lenders require with a draw request. On a home construction contract, section 1311.011(B) adds these rules:

  • Contractor's affidavit before payment. A lending institution can't pay the original contractor until the contractor gives an affidavit saying everyone who did work or supplied materials has been paid in full, or listing each unpaid claim by name and amount.
  • The owner can hold payment until you provide that affidavit, if they ask for it.
  • Joint checks. The owner or lender may pay you and a sub or supplier jointly in exchange for their lien release.
  • Disputed amounts. If a sub won't give a release because the amount is in dispute, the owner and lender hold back that amount from you until the sub confirms payment, gives a release, you post a bond for it, or the sub's time to file a lien runs out with no lien recorded.
  • Lender notice. Once a lender gets written notice of a lien claim, failing to get a release from that claimant is evidence of gross negligence, so expect the bank to ask for it.

In practice, collect releases as you pay subs and suppliers, and keep them with the draw they belong to. If you hold retainage, track which releases cover it. Use the forms your lender or attorney gives you. For the rest, see the bank draw process for home builders and what a draw request is.

The Homeowner Side on a Remodel

Your remodel and custom home clients are protected by section 1311.011:

  • Paid in full means no lien. If they pay you the full contract price before they receive a copy of a lien affidavit, no one has a lien, and sub and supplier liens filed after that are void unless there's fraud.
  • Sub liens are capped. If they haven't paid in full, all sub and supplier liens together can't be enforced for more than they still owe you, minus the cost to finish the contract.
  • Owner's affidavit. They can record an affidavit of full payment with the county recorder. A claimant who gets written notice of that payment and doesn't release the lien within 30 days owes the owner's damages, including court costs and reasonable attorney fees.
  • Paying twice. If you don't pay a sub, the Ohio Attorney General's home improvement guide tells homeowners to withhold that amount from you and write a joint check to you and the sub in exchange for a lien release.

The guide also tells borrowers to ask their lender how to protect the property from liens. A clear construction payment schedule helps too.

How to Protect Your Pay and Your Client's Home

To protect your right to get paid

  • Keep dated records of your first and last day of work. Lien deadlines run from the last date, so calendar it the day you finish.
  • On jobs that need one, get the notice of commencement, and ask in writing if it isn't posted.
  • Make sure your contract and the Ohio contract rules for home jobs line up.

To keep subs' liens off your client's home

  • Pay subs and suppliers on time out of each draw, and get a release when you pay.
  • List any unpaid claims honestly on the contractor's affidavit, and settle or bond disputed amounts before they hold up a draw.
  • Put every extra in a written change order so what's owed stays clear.

Keeping the Payment Paper Trail Straight

Smart Builder 360 doesn't file liens or notices, and it doesn't make lien waiver forms or collect signatures on them. Its bank draw form workflow keeps draw details, schedules, cost information and supporting documents, including lien waiver details, organized with each draw, so you can find them when the lender asks. The project statement shows what's been paid and what's still owed, which is what an owner or lender wants to see. Documented, approved change orders keep the contract price clear. On a remodel or a new home, that means each draw's documents and lien waiver details stay with the job, approved change orders are tracked, and the project statement shows what's been paid and what's still owed. Smart Builder 360 is built by builders for builders and endorsed by The Ohio Home Builders Association (OHBA).

Try Smart Builder 360 free for 30 days.

For remodels and new homes: bank draw forms, project statements and approved change orders, with each draw's documents and lien waiver details in one place. No credit card required.

Start my free trial

Frequently Asked Questions

How long do I have to file a mechanics lien in Ohio?

For a one- or two-family home or a condo unit, 60 days from the last day you performed work or furnished materials. For most other jobs, 75 days. Serve a copy on the owner within 30 days after filing.

Who files the notice of commencement in Ohio?

The owner who contracts for the work records it with the county recorder before work starts. If the owner doesn't, the original contractor can demand it in writing. If it still isn't recorded by the later of 10 days after work starts or 3 days after that demand, the contractor may record it, and the owner owes the costs. On a custom home or remodel for an owner who lives there, it's only needed if the lender requires it.

What happens if a sub misses the notice of furnishing deadline?

A late notice of furnishing still works, but it only protects work and materials from the 21 days before it was served and after. Amounts from earlier lose lien rights. No notice is needed if no notice of commencement was recorded.

How long does a mechanics lien last in Ohio?

Six years after the affidavit is filed, or longer if a suit to enforce it is filed in that time. If the owner serves a notice to commence suit, the claimant has 60 days to sue or the lien is void.

Can a sub put a lien on my client's house if the client paid me in full?

Not on a home construction contract, if the client paid the full contract price before receiving a copy of a lien affidavit. The client can record an affidavit of full payment. If the client hasn't paid in full, sub liens are capped at what the client still owes you, minus the cost to finish.

Does Ohio require lien waivers before a construction loan draw?

On a home construction contract, the lender can't pay the original contractor until the contractor signs an affidavit that everyone has been paid or lists each unpaid claim. Lenders also commonly ask for lien waivers.