General conditions in construction are the job-site costs of running a project that don't belong to any one trade: supervision, temporary power and water, dumpsters, portable toilets, site protection, cleanup and equipment rental. Most of them run by the week, so they grow when a job runs long.
- What Are General Conditions in Construction?
- What Goes Into General Conditions?
- General Conditions vs Overhead vs Profit
- How Do You Estimate General Conditions?
- Where Do They Show Up on a Schedule of Values or Draw?
- Common Mistakes on New Builds and Remodels
- What Does "General Conditions" Mean in a Contract?
- Frequently Asked Questions
What Are General Conditions in Construction?
Every job has costs no sub will put on a bid. Somebody has to run the site, keep the power on and haul the trash. General conditions are what it costs to keep the job open until it's done.
The term has two meanings, and you'll hear both:
- General conditions costs: the section of your estimate and budget for those job-site costs.
- General Conditions as a contract document that sets the rules for the job.
What Goes Into General Conditions on a Home Build or Remodel?
On a residential job, the list usually includes:
- Supervision: your own or your lead carpenter's hours on this job. If you run the job yourself, price your time.
- Temporary power, water and heat.
- Dumpsters and haul-offs.
- Portable toilets.
- Site protection: fencing, erosion control, floor and dust protection.
- Ongoing cleanup and the final clean.
- Equipment rental for the whole job, like a storage container.
- Permits and fees, on some estimates.
- Job-specific insurance, like a builder's risk policy, when your contract puts it on you.
Sort them the same way on every job, or jobs won't compare and something gets counted twice or not at all.
How Are General Conditions Different From Overhead and Profit?
General conditions belong to one job. Overhead belongs to the company. Profit is what's left.
| Bucket | What it covers | Where it goes |
|---|---|---|
| General conditions | Costs of running this one job site: supervision, dumpsters, temp power, toilets, cleanup | In the job's cost |
| Overhead | Costs of running the company: office, software, office staff, marketing | Covered by your markup, spread over all jobs |
| Profit | What you keep after cost and overhead | The rest of your markup |
Leave general conditions out of the cost and your markup has to cover three things instead of two. Usually your profit gives.
How Do You Estimate General Conditions?
Most general conditions are driven by time, not job size, so estimate them from the schedule.
- Set the duration. How many weeks will the site be open, start to final clean?
- Give each item a weekly cost. Use bills from past jobs and current supplier quotes.
- Multiply by the weeks on site.
- Add one-time items. Fence setup, the last dumpster haul, the final clean.
- Check it after the job. Compare what you planned in your construction budget with what you spent, and fix your rates for next time.
A worked example
Example numbers only, not market prices. Say an addition will be on site for 16 weeks:
| Item | Per week (example) |
|---|---|
| Supervision (share of a superintendent's week) | $900 |
| Dumpster swaps | $250 |
| Site protection and cleanup | $150 |
| Temporary power and heat | $60 |
| Portable toilet | $40 |
| Weekly total | $1,400 |
$1,400 a week times 16 weeks is $22,400. Add $1,200 of one-time items and the job carries $23,600 in general conditions. Now say the job runs three weeks long. That's another $4,200 you never priced, and it comes straight out of your profit.
In Smart Builder 360, a project estimate organizes costs by category and line item, so "16 weeks at $1,400" goes in as a line like anything else. Estimated vs Actual then tracks actual cost and cost variance as you enter costs during the job. When a change order adds weeks, add a general conditions line to it so the extra time shows up in Estimated vs Actual. See how to track job costs as a contractor.
Price the weeks on site, not just the materials. Try Smart Builder 360 free.
Start my free trial30-day free trial, no credit card. $199/month after that, plus $20 per extra user.
Where Do General Conditions Show Up on a Schedule of Values or Draw?
On a schedule of values, general conditions may get their own line, or the lender may roll them into stage percentages. Bill that line as time passes, not up front. A big first-draw bill looks like front-loading, and lenders watch for that.
Ask the lender how they want them shown before the first draw request, so your estimate and their form match. Smart Builder 360 creates bank draw forms in the same app as your estimate, so the draw request and the budget come from one place.
Common Mistakes on New Builds and Remodels
- Leaving them off small jobs. A bath remodel still needs a dumpster, protection and your time.
- Forgetting the client lives there. Dust walls and daily cleanup in an occupied home take real hours.
- Guessing a round number. It doesn't grow when the job does. Weeks times a weekly rate does.
- Leaving them off change orders. A change that adds two weeks adds two weeks of general conditions. Price them in.
- Missing new-build site costs. Forgetting the temp pole and meter fee, the stone construction entrance and the final survey.
- Skipping lead-safe costs on older homes. Lead-safe (RRP) setup, containment and cleaning verification on homes built before 1978.
- Burying supervision in overhead. Time your lead carpenter spends running the job is a job cost.
A clear scope of work that says who handles the dumpster, protection and final clean heads off arguments at the end.
What Does "General Conditions" Mean in a Contract?
In a contract, General Conditions is the section that sets the ground rules for the job. The best-known example is AIA Document A201, the American Institute of Architects' General Conditions of the Contract for Construction. It covers the roles of owner, contractor and architect, changes, time, payments, insurance and bonds, and disputes.
A201 is common when an architect manages the contract. Most residential builders use their own contract with the same topics. Read that section closely: it decides how changes get approved and how you get paid.
Frequently Asked Questions
What are general conditions in construction?
They're the job-site costs of running a project that don't belong to any one trade: supervision, temporary power and water, dumpsters, portable toilets, site protection, cleanup and equipment rental. Most of them run by the week, so you estimate them from how long the job will be open, and they go up when the job runs long.
Are general conditions the same as overhead?
No. General conditions are costs of one job, like that job's dumpster or the time your superintendent spends on it. Overhead is the cost of running your company, like the office, software, office staff and insurance that isn't tied to one job. General conditions go into the job's cost. Overhead gets covered by your markup.
How do you calculate general conditions?
List every item, give each one a weekly cost and multiply by the number of weeks the job will be open. Then add one-time items, like setting up a fence or the final clean. Example numbers only: $1,400 a week for 16 weeks is $22,400, plus $1,200 of one-time items, for $23,600 in general conditions.
Are permits part of general conditions?
Sometimes. Some builders carry permits and fees in general conditions, others give them their own line in the estimate. Either way works. What matters is that permits are in the estimate once, not missing and not counted twice, and that you set it up the same way on every job so your numbers compare.
Do general conditions get marked up?
On a fixed-price job, usually, yes. They're a cost of the job, so your markup applies to them like any other cost. On cost-plus or guaranteed maximum price contracts, the contract decides which general conditions the owner pays for. On those jobs, or on a lender budget, check the contract or the lender budget before you put a fee on general conditions.
What is AIA A201?
AIA Document A201 is the American Institute of Architects' General Conditions of the Contract for Construction. It sets the ground rules for a job: the roles of owner, contractor and architect, changes, time, payments and completion, insurance and bonds, correcting work, and claims and disputes. It's common on jobs where an architect manages the contract.